Krino Energy Service Scope:
- The de-montage of the existing 600m long 1×185 XLPE MV line from both the IGA scope substation and the THY scope transformer, as well as from its current route.
- Determination of the new route and project design.
- Connection of cable terminals.
- Laying a new 1×185 XLPE MV line along the determined new route and connecting it to both the IGA scope substation and the THY scope transformer.
- High-Pod Test and Commissioning